Can the export log to Primavera P6 provide activity IDs for errant logic/relationships?

I often have to integrate MS Project and Primavera P6 data into a shared database. I found Synchro is a good tool to do this. Importing an MS Project xml file to Synchro then exporting to a P6 database will flag errant logic/relationships, etc. which I can then go and fix in Synchro or P6. The error log gives task descriptions but not task IDs. 

Is it possible to show task IDs in the error log?



  • Andrew Taylor
  • May 10 2016
  • FAQ
Company Red Arrow
  • May 10, 2016

    Admin Response

    Adding the Task ID to the export report is a great suggestion. Thanks!

    You may also want to check out the Reschedule Report available in the Home ribbon. This report will find and list the following statistics (you can choose which to include in Options>Gantt Chart>Rescheduling>Report). You can copy the text of the report for reference, then after the report is run you can view the results by category in Navigator>Alerts where you can double click on a listed task to jump to it in the schedule

    • Numer of Tasks
    • Number of WBS Summary tasks
    • Number of Logic Links
    • Number of Task in Planned Status
    • Number of Tasks In progress 
    • Number of Completed Tasks
    • Check for Logic cycles and list tasks involved in each cycle
    • Tasks with Violated constraints
    • Out of sequence tasks
    • Unscheduled links
    • Tasks Skipped on reschedule
    • Early tasks
    • Late tasks
    • Tasks with actual dates in future
    • Tasks without predecessors
    • Tasks without successors
    • Tasks with constraints
    • Critical tasks
    • Subcritical tasks
    • Negative lag links
    • Long lag links
    • Ladder task chains