Ressource leveling when task is started

I don't seem to be able to use ressource leveling, for a ressource if that ressource is currently active (a task where it is assigned is started).

Is this possible to do? I can only seem to make it work for tasks, where the ressources assigned is not active.

 

Thank you in advance.

  • Thomas Anthony Pedersen
  • Jun 28 2016
  • Future improvement
Company SCHOU BIRKENDORF arkitekter ApS
  • Jul 19, 2016

    Admin Response

    Currently, if a task is started, Synchro will ignore that task completely when resource leveling and this means that the tasks you are talking about will not move because they 'clash' with a task that is completely ignored by the leveler.

    This has been added to the list of future improvements improvements.