Is it possible to see the tasks roling in the animation avi?

I would like to see the tasks show up when the 3D animation is runing for the avi.

  • Guest
  • Feb 17 2017
  • FAQ
Company Magil Construction
  • Apr 6, 2017

    Admin Response

    1. Create a new Task Filter and check the box to enable it

    2. In the General tab, activate "Look Ahead"

    3. In the Look Ahead tab, change the Look Ahead Duration to 1d and select Focused Time. Enable "Include Overlapping Task"

    4. Now when the Gantt window shows in the AVI, only the active tasks will appear and will update as the animation proceeds

     

    Alternatively, if you wish to show only the name of the active tasks (and not the Gantt chart):

    1. in the AVI Export window, go to the Textural Frames tab

    2. From the dropdown, select Active Tasks (or Active Filtered Tasks)

    3. Change the settings if desired

    4. Click "Add new frame"

    5. In the Content tab, check the box to enable the text frame, then arrange it on the preview canvas

  • Attach files
  • Guest commented
    February 17, 2017 16:02

    The roling event of tasks following what we see in the 3D animation. 

  • Guest commented
    April 18, 2018 05:51

    I have the same problem.

    I want to show the task and gantt chart which link the assign object.

  • Admin
    Kate Hester commented
    April 18, 2018 09:48

    Use the first option described above.

    You may also wish to switch Plan>Grouping> to List rather than WBS to hide the summary bars, or use Expand>All to show the subtasks under the summaries

    Additionally, in Options>Gantt Chart>Animation, you may change Focus Time Screen Position to "Left" to show more of the future tasks, or to "Center" to show both prior and future tasks