Synchronise from 3D model without losing assigned tasks

I have a complete 4D model with combined 3D models. (Revit+Civil3D combined in Navisworks and exported with the pug-in) When I try to synchronise my resources I have a ton of options (skip, consolidate, synchronise) per object. I have tried a lot of combinations, but everytime I will lose my assigned resources. What are the best settings for this synchronisation?

  • Yorick Laarhoven
  • Mar 20 2017
  • FAQ
Company
  • Mar 20, 2017

    Admin Response

    When Synchronizing from an SPX file generated from the Navisworks plugin, these are the settings that will retain all of your assignements of resources to tasks (and update the User Field values)

    Skip All except: Resources, 3D Entities, 3D Assignments, User Fields, User Fields values should be set to Integrate


    If you are importing the tasks from Navis as well as objects, additionally set Tasks, Links, and Resource Assignments to Integrate:

  • Attach files
  • Yorick Laarhoven commented
    March 20, 2017 11:34

    Thank you for your quick response. I've tried these settings, but still losing assignments...

  • Admin
    Kate Hester commented
    March 20, 2017 11:45

    What version of the navisworks plugin are you using? Try upgrading to the latest version for Synchro PRO 2016. There have been improvements to help with synchronisation

    https://synchroltd.com/downloads/

  • Yorick Laarhoven commented
    March 20, 2017 12:00

    I have version 5.3.3.1 installed. This shouldn't. be the problem.

  • Admin
    Kate Hester commented
    March 20, 2017 12:02

    Please send your files to support@synchroltd.com for further investigation

  • Peter Vlaar commented
    March 21, 2017 09:41

    Hi Yorick, Try to create GUID's when you export the SPX and dont forget to save the file after you export the SPX.

  • Vishal Verma commented
    February 1, 2018 10:41

    I am also facing the same issue. Is there any solution of it.