Not possible to choose 'integrate' when synchronising MS Project XML

When Synchronising my MS Project-XML file, I can't select the 'Integrate'-option for any of the fields.

There are a lot of deleted tasks in the MS Project file, and I've created own tasks in Synchro.

- Synchronise deletes the deleted tasks, but also deletes my own Synchro-tasks

- Consolidate keeps my own Sychro-tasks, but does not delete the deleted MSProject-tasks

  • Lennart Lippens
  • May 17 2017
  • Future improvement
Company BAM
  • May 17, 2017

    Admin Response

    Thanks for the feedback. We've added this to the list of improvements for our next release.

    As a workaround in the meantime, try adding a user field (eg. with the current date) to all the tasks in MSP before exporting to XML. After synchronising from MSP using "Consolidate" option, filter for all the tasks that do not have the updated user field value and delete them manually