I have a question concerning clash test dynamic in Synchro. There are 2 scenarios:

1. Scenario 1: two task with 10h of delay and 3D path assigned to crane (let's see the sp file). The clash result show 2 clashs. That's correct.

2. Scenario 2: the same sp file but this time we don't have delay between two task (FS link). Run the same clash test, we don't have the clash. But in 3D view, we see clairly it should have the same clash as scenario 1.

Can you explain why we have the different results in these case and what are the parameters we need to define to have a raisonable result for clash test?

 

Thank you in advance!

  • Guest
  • Jul 11 2017
  • Future improvement
Company
  • Jul 27, 2017

    Admin Response

    This is a bug and has been reported to our developers for fixing. Thank you for letting us know!