my "reschedule" feature is not functioning correctly. my schedule shows 7/11/2018 as a finish date and when i aske it to reschedule it changes the finish date to january 2020.

my reschedule feature is not functioning.

  • Guest
  • Jul 27 2017
  • FAQ
Company LInbeck Group
  • Jul 27, 2017

    Admin Response

    Check your settings in Navigator>Project>Details:

    - Check the Data Date - should usually be set to Manual with the last schedule update as the date

    - Check the setting for Schedule - should usually be set to ASAP

    - Check the Schedule From option - should usually be set to Data Date

    You may additionally check your settings in Options>Gantt Chart>Rescheduling>Parameters: