Planning a Month instead a Day

Is it possibile to plan with units month in stead of days, i sort out that i can duration display format tot months but if i make my Gantt planning and fill in "x" month is doesn't take a full month. Any advice? 

  • Guest
  • Jul 31 2017
  • FAQ
Company Inspec
  • Jul 31, 2017

    Admin Response

    When entering durations in months (eg. 1M), Synchro simply multiplies the number of months by the Number of Working Days per Months as set in Options>General>Duration Display Format (default: 22 days)

    Similarly, when displaying the duration in months, the duration in days is divided by the number of working days per month to get months. For example, Aug 1 2017 to Aug 31 2017 is displayed as 1M, 1d because there are 23 working days between those dates (inclusive) and the default working days per month is 22.

  • Attach files
  • Guest commented
    August 1, 2017 09:23

    Thanks! I will edit the calander to full work weeks (7days a week) and will set the working days a month to 30 then it will fit in better! Thanks!