I created a user field called POUR DATE which is the date concrete is going in. I have an other user field which is CUBIC YARDS PLACED. Is there a way that in can put CUBIC YARD user field with relative to POUR DATE user field in the same user field graph. See picture for reference.

I want the CY user field graph to spike at the pour date. not the start date. is it possible?

  • Dilip Reddy Allam
  • Aug 8 2017
  • FAQ
Company
  • Aug 14, 2017

    Admin Response

    There is currently no way to have the User Field graph be tied to dates other than the planned task dates. 

    I would recommend adding the User Field columns to the task table and exporting to Excel (File>Export>Microsoft Excel) to create the graph there.

    Alternatively, you could create subtasks under the existing task for the different steps involved, including a Pour task whose Start  matches the POUR DATE user field, then copy the CUBIC YARDS PLACED User Field values to the Pour subtasks - then the User Field graph in Synchro would spike on those Pour dates

  • Attach files
  • Dilip Reddy Allam commented
    August 14, 2017 15:08

    Thanks! The Idea is to pull everything out of synchro! so I would say the second idea is better. I am thinking about creating a totally separate scenario for pour dates.