Export to MS Project



How does synchro (or MSP) manage the double link constraint. 

Meaning having to links on two same tasks. 

What happens when importing on MSP?


Thanks for the answer :)

  • Mathieu Farine
  • Nov 27 2017
  • FAQ
Company Student
  • Nov 27, 2017

    Admin Response

    On Export to MSP, Synchro provides a warning for tasks that are linked more than once. E.g.:

    Warning: task [Task 1] links the task[Task 4] more than once.

    On import of the XML to MSP, only the first link (order of creation) is retained 

  • Attach files
  • Mathieu Farine commented
    November 27, 2017 11:09

    Okey perfect!

    Thank you!