Store period performance

hi,

 

exist a way to fix the percentage of work?  we check every month the status of our building status and register the percentage of works completed, we would like to fix this periodic check directly in synchro. In primavera this function is called "store period performance"

  • raoul Pletl
  • Dec 19 2017
  • Future improvement
Company
  • Dec 19, 2017

    Admin Response

    Synchro does not currently have the ability to "store period performance" This is on our list of future improvements.

    You can enter task percent complete by automatic, manual, duration, physical quantity, or resource units - but you will not be able to tell how much was completed in each period