Calendar

Hi, It is possible to create a calendar with only  x working days? I need these dates to be specific, so when I start with a new calendar and I try to "clean" the whole week, it says that I must keep at least one working day a week, wich alters the duration of all my planned activities, 

Thanks, 

Cheers

  • G G
  • Feb 21 2018
  • FAQ
Company
  • Feb 22, 2018

    Admin Response

    You cannot "clear" a entire workweek for an entire calendar, but you can clear it for multiple years (e.e. as long as the project runs). When setting a day to Non-Working, choose "Each [Monday/Tuesday/etc] in the current year" instead of "Every [Monday]" you can repeat this for multiple years if desired. Then add in your specific working days.

  • Attach files
  • G G commented
    February 22, 2018 22:54

    OK, thanks, that is what we are doing at the moment...